Work Effort wrong calculations and bars split
In the Open Standard
George BoltonMember for 20 years 11 months
- Created
- 1
- 3
0
Hi, I’ve been getting errors when loading resources into a MS Project schedule. Calendar is configured as 8 hours/day from Monday through Friday. Then, I input taks and their respective durations (in days). Later on, I create my resources and load them into the tasks. Work Effort field (man-hours) sometimes get wrong calculations and sometimes the software splits the bar (with dots between the split bars). Could anyone tell me if I’m doing something wrong or maybe I need to setup something or whatever? I will appreciate any help on this issue. Thank you.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?