overtime calculations

Vinod RaturiMember for 20 years 2 months
Created
2
4
0
Hi ,

I have a resource who works for total 11 hrs i.e 8 hrs of regular work and 3 hrs of overtime work.

How to feed this information in MS project , so that we know on a particular day what is its cost to co.

2 replies

Oldest first
  1. 0
    Vinod Raturi ·
    hi ,

    once i entered resource cost in Resource information dialog box , can someone tell me as why cant i delete that information once i have clicked OK.

    OR please tell me how i can revise that information.
  2. 0
    Zhang Haixiang ·
    Hi,

    you can input these info. in ’Resource Usage View’
    insert a column ’overtime work’

    as for your example, put 11hrs in work, and 3hrs in overtime work

    for your 2nd question, i’m afraid the first row can’t be deleted.