MSP Graph Usage / Gannt Usage

Chris MurrayMember for 22 years 7 months
Created
2
4
0
All,

Quite simply, I’ve done it once before ONCE. I want a sheet with the resource usage graph at the top and the Gannt Levelling at the bottom.

Please help

2 replies

Oldest first
  1. 0
    John Garay ·
    Sorry, this post has working links...

    "Quite simply, I’ve done it once before ONCE. I want a sheet with the resource usage graph at the top and the Gannt Levelling at the bottom."

    Hello Chris -
    I’m not sure exactly what you are looking for...
    But maybe I can help.

    My company, DecisionEdge, offers an add-on graphics program for Microsoft Project. If we don’t have your particular graph among the 70+ already included in the software, if you send me a sample, I’ll add it to our software...

    Here are samples of the graphs for MSP we have now:
    http://www.decisionedge.com/microsoft_decisioncharts_gallery.htm

    You can send me a sample directly at
    jgaray@decisionedge.com
    (A sample can be a screen image, a scanned copy, a sample from a different program, a hand drawing, ANYTHING that illustrates what you want)

    Regards, John Garay
  2. 0
    Alexandre Faulx-Briole ·
    Hello,
    Window, Split
    Click the upper pane and select the view you want
    click the lower pane and select the view you want
    Tools, Organize
    copy the current view you’ve just created to the global.mpt file and give it a new name
    Alexandre