Work Column in Task Usage Sheet Showing Zero

Kumar SMember for 16 years 8 months
Created
6
5
0

Hello Guys,

I have finished adding activities and scheduling with my project.Now whne i want to see the work distribution in Task usage sheet it is showing as Zero What is the reason...

 

Please guide me ....

6 replies

Oldest first
  1. 0
    Raymund de Laza ·

    The reason is that your

    The reason is that your Project is incomplete... You did not add the Resources of your activities.

  2. 0
    Kumar S ·

    Hei, Ok ..If that is the case

    Hei,

    Ok ..If that is the case then,I had not assigned resources to my previous Project also and  it was showing the Work Days Correctly..

    I want to ask if it necessary to add Resources If i have to monitor the progress in MSP...

  3. 0
    Alexandre Faulx-Briole ·

    Kumar,sorry to say that, but

     

    Kumar,

    sorry to say that, but you are certainly wrong: it is not posisble to have Work if you do not have resource assignments

    beside, you do not need resources to monitor your project; you will enter Actual Duration or (Duration)% Complete instead of Actual Work or Work% Complete

    Alexandre

  4. 0
    Kumar S ·

    Thanks Alexandre. U r right.I

    Thanks Alexandre.

    U r right.I had to assign the resources to get the Work column Values.

    Since i dont want to add the resources in my schedule and monitor the project based on the duration I have manually put the work days same as duration.

     

    Regards,

  5. 0
    Trevor Rabey ·

    You can indeed have work

    You can indeed have work assigned to a task without assigning a resource to the task.

    Try a test. Make a task, 10 days duration. Show the work column. Type in 100. Switch to Task Usage View and there it is, spread evenly across the days.

    Of course, even though you can do it, it is a very bad idea and you should assign the resources.

  6. 0
    Alexandre Faulx-Briole ·

    Trevor and Kumar,my mistake!

    Trevor and Kumar,

    my mistake! Trevor is right, it is possible to enter a value for Work eventhough there is no resource assigned to a task;

    however, in my opinion this value will not represent "real" work, and MS Project will not be able to establish a relationship between the task duration and the task work

    it is possible, but it should be avoided

    Alexandre

Log in or join to reply