Master and Sub-Projects??

Allison RobbMember for 21 years 2 months
Created
3
2
0
Is there a clever way of setting up a master project within MS Project 2002. We are trying to reduce the amount of manual updates from plans submitted to a central project office.

3 replies

Oldest first
  1. 0
    Paul Harris ·
    You may use the Insert, Project Command and insert as many projects as you like.

    I suggest you use this option with caution, there are many issues with this option.

    I prefer just cutting and pasting the tasks from one project into another, but then the calendars have to match before doing this. You may consider setting an Interim Baseline to confirm the tasks that are passed in are calculating correctly after insertion.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Tony McClennon ·
    Would suggest that you set up a template to be used by all of the sub-projects, which have common calendars, customised fields, headers/footers, bar styles etc.

    You may also wish to consider using one of the text fields as a predefined task numbering system e.g.:

    XX-YYY-ZZZZZ

    where XX relates to the sub-project, YYY is the high-level WBS within the sub-projectm and ZZZZZ are the unique task IDs.

    Hope this is of use.
  3. 0
    Robyn Brown ·
    Hi All,

    It is possible to provide a quick and easy way to consolidate all the projects. Once the filters etc. are defined it can be done automaticccccaly.


    Regards
    Robyn

Log in or join to reply