Multiple Master Projects (MSP)
In the Open Standard
Paul SmithMember for 19 years 8 months
- Created
- 3
- 3
0
Has anybody had experience in a matrixed (functional/project) organisation where an individual schedule may be a subproject of more than one Master Project hierarchies.
For example I may have Functional Master files at Design, Build and Test teams and Project Masters at Proj#1, Proj#2 etc. I would build multiple subprojects at the intersection of these; eg. I would build a schedule to cover the testing in project 2.
I am hoping I can open the Test Master and see the subprojects for each Test-P1, Test-P2 etc and that all data will roll up accordingly. Equally I could open Up Proj#1 master and see P1-Design, P1-Build and P1-Test subprojects.
Your thoughts appreciated?
Paul.
For example I may have Functional Master files at Design, Build and Test teams and Project Masters at Proj#1, Proj#2 etc. I would build multiple subprojects at the intersection of these; eg. I would build a schedule to cover the testing in project 2.
I am hoping I can open the Test Master and see the subprojects for each Test-P1, Test-P2 etc and that all data will roll up accordingly. Equally I could open Up Proj#1 master and see P1-Design, P1-Build and P1-Test subprojects.
Your thoughts appreciated?
Paul.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?