MsProject to P3 PP

Farid SalmanovMember for 20 years 6 months
Created
15
4
0
Guys and Girlies,

I know we have been discussing this issue for quite a long time but still I believe have not come to a single solution.

I need to transfer a MsProject 2000 file into Primavera P3 version 3.1. What is the best way to do that ?

Many thanks in advance

15 replies

Oldest first
  1. 0
    Paul Harris ·
    There are several methods and they all have advantages and disadvantages. There is a technical article on my web site that may assist.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Farid Salmanov ·
    Dear Paul,

    Thanks for your feedback but I did not manage to download that article from your web-site, can you please paste the exact link of the article’s whereabout

    Many thanks in advance
  3. 0
    Paul Harris ·
    http://www.eh.com.au/technical_papers.htm
  4. 0
    Farid Salmanov ·
    Thanks Paul

    I have downloaded the article and figured out the way I can do transfer.

    The question I have got now is: in your article you refer to "MPP to MPX conversion utility" availability at the Primavera.com but I could not find it there, do you have this software available in your possession if yes, can you please me at farid.salmanov@rolls-royce.com

    Many thanks in advance
  5. 0
    Paul Harris ·
    This is a P3 menu item under Tools.

    Regards

    Paul E Harris
  6. 0
    Farid Salmanov ·
    Thanks Paul,

    This under tools is P3 to MPX and vice versa converter.
    To use this I need my mpp file transferred to mpx, and I use MsProject 2000. How can I transfer mpp into mpx, that’s my bottleneck
  7. 0
    Alexandre Faulx-Briole ·
    Farid,
    everything is clearly explained in Paul’s paper, page 4, item 2.3
    should you need the Sciforma utility, that works well, just send me a PM and I will mail it to you.
    Have a good day
  8. 0
    Farid Salmanov ·
    Thanks Alexandre,

    I am new to this forum, do not know how to send PM. My e-mail address is farid.salmanov@rolls-royce.com. Can you please send this to that account.

    Thanks in advance
  9. 0
    Farid Salmanov ·
    Alex,

    Thanks for the file, it works OK with small projects but does not work with big ones (about 1000 activities)
  10. 0
    Alexandre Faulx-Briole ·
    Farid,
    I have not heard of any limit in size; give it a try and tell me.
    All the best, bqa 3la kheir
  11. 0
    Farid Salmanov ·
    Alex,

    When I try to convert small projects with 10-15 activities it works OK, but as I try bigger ones it shows "Run-time error ’5’, Invalid procedure call or argument.

    Thanks
  12. 0
    Alexandre Faulx-Briole ·
    Farid,
    how large is your project?
    is ttaht mpx2000 or P3 that gives you the error?
    Alexandre
  13. 0
    Farid Salmanov ·
    MsProject

    The file has about 1000 activities and it is about 2 MB
  14. 0
    Alexandre Faulx-Briole ·
    Farid,
    Your PM says "MSP 2000"; do you mean MS Project is sdending a error message, or is it the MPX2000 utility?
    This piece of software works well with any size of project; before saving your project in MSP, make sure all the durations dipslay in the same unit and display the dates in date/time format.
    In case it does not work properly, send me your file.
    Alexandre
  15. 0
    Farid Salmanov ·
    Sorry, it is of course utility that produces the error.
    Will send you a file down today

    Thanks