Trouble Exporting MSProject 2007 files to Primavera Contractor

Geof K. BakerMember for 15 years 3 months
Created
1
6
0

I am having huge problems trying to export a project created in MS Project (by my owner) into Primavera's P4 Contractor.

I need help so that I don't have to recreate the entire project from scratch. Anyone know a way or a file conversion utility to accomplish this?

1 reply

Oldest first
  1. 0
    William (Bill) Drew ·

    Primavera is not compatible

    Primavera is not compatible with MSP 2007. You must save your MSP either as MSP 2003 or as an XML file and then import it into P4. 

Log in or join to reply