Skip to content

Constraint

Hemanth KumarMember for 23 years 11 months
Created
2
2
0

I am doing a hourly schedule
how can i constrain an activity to start at a specified time ie the activity must start on 12/05/06-09.00 Hrs


Thanks

Hemant

2 replies

Oldest first
  1. 0
    W A ·
    more details is requiered, is it a contractual start or not? if it is not in the contract the consultant (or any reviewer) will reject the constrained schedule, the logic must flow.

    Anyway, i’ll assume that it is a contractuall constraint, may be the owner will furnish certain planet to the project, Also, the I’ll assume that you know the constraints type, and you need the Must Start On type specifically.

    1) double click the activity,
    2) click the Advanced tab
    3) from the constraint type drop-box select must start on
    4) specify date.

    click ok

    enjoy
  2. 0
    Zhang Haixiang ·
    MSP only show date under default setting.
    from "Tools" menu click "Options" click "View" tab, under "Date format" choose a format showing date and time.
    then you can input date and time in the start/finish column.
    this will add start no earlier/finish no earlier constraint.

    actually you can directly input e.g. "6/25/06 9:00 am" in start/finish field (or advanced tab )to add constraint

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?