resources kept getting mixed up! AAARGH!
In the Open Standard
Marko RoosenoMember for 20 years 3 months
- Created
- 5
- 3
0
Hi Planners.
I’ve worked out a project with resources on multiple rates. Please note this does not mean normal/overtime rates, but depending on their positions assigned within the projects, i.e.
Mr X - Project leader
Ms A - Project leader
Mr X - Senior Interior Designer
Mr Y - Senior Interior Designer
Ms B - Assistant Interior Designer
Here Mr X has two options of assignment: as project leader, or as senior interior designer
If I assign Mr X as senior interior designer (which has a lower rate prorata than as project leader) for some reason the next time I open the file Mr X automatically goes up to become a project leader.
Is this normal? How can I avoid this happening again?
Cheers
M
I’ve worked out a project with resources on multiple rates. Please note this does not mean normal/overtime rates, but depending on their positions assigned within the projects, i.e.
Mr X - Project leader
Ms A - Project leader
Mr X - Senior Interior Designer
Mr Y - Senior Interior Designer
Ms B - Assistant Interior Designer
Here Mr X has two options of assignment: as project leader, or as senior interior designer
If I assign Mr X as senior interior designer (which has a lower rate prorata than as project leader) for some reason the next time I open the file Mr X automatically goes up to become a project leader.
Is this normal? How can I avoid this happening again?
Cheers
M
5 replies
Oldest firstLog in or join to reply