calander view

Vinod RaturiMember for 20 years 2 months
Created
1
3
0
hi ,

whenever i switch from gantt view to calander view , every time it starts from year 1988. Then i start scrolling from 1988 to 2006 .

Please guide me , as to how to avoid this situation.

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hi,
    this behaviour is not specific to Calendar View; for an unknown reason close to a bug, most of the task views in all versions of MSP display a time period far from the project dates: the "Gantt Chart" view is the only one to understand that the user is interested in viewing the project dates and not the winproject.exe file date.
    There is nothing that can be done, except scrolling back to the project dates.
    Alexandre