Creating Timescaled Resource Data Reports

Paul HarrisMember for 25 years 6 months
Created
1
3
0
I have a client with a Microsoft Project schedule that has multiple projects in one schedule:

1. Projects and Areas identified using Outlining
2. Multiple resources assigned against activities
3. Project, Areas, Clients and Funding Sources identified in Text Columns, thus Projects and Areas are available in both outlining and Text columns.

They require reports with:

The Horizontal axis showing Quarters, Months or Weeks (a report for each)
Vertical axis showing
One Text Column (Say Client)
Second Text Column (Say Funding Source)
Budget/Actual/To Complete
Resource Quantity and/or Resource Cost

My understanding is after some experimenting that:
1. Analyze Time Scaled data in Excel does not export Resources
2. Exporting to Excel does not support timescaled data and long activities that span multiple periods will not be split over periods
3. This report is not produced by Views without massive amounts of irreverent detail
4. This report is not produced by Reports

Does any one have a technique for simply creating this type of report?

Regards
Paul E Harris

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hello Paul,
    You should ask Jean-François Morvan, STK Management, about it.
    JF has been working on vba solutions around ms project since the very beginning, he is a member of IIL France, ...
    http://www.stk-management.fr/
    infos@stk-management.fr
    Feel free to recommend yourself from my mail and name.
    Regards

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?