BASELINE VS ADDITIONAL TASKS
In the Open Standard
Julian CoetzeeMember for 20 years 4 months
- Created
- 10
- 5
0
Good Day
I am experiencing a interesting situation, I draw up a plan or programme and once it is approved and signed off, I save the baseline and show it on the Gantt bar section so that one can see Planned vs Actual graphically.
What is the correct way to manage the programme if during the course of the project, additional tasks crop up and need to be added, as they might influence the critical path. If I add them in later, that menans they are not part of the original baseline and appear as blanks. Do I then select these "new" tasks and save the baseline again? I don’t want the original baseline finish to shift.
I hope what I am asking makes sense?
I am experiencing a interesting situation, I draw up a plan or programme and once it is approved and signed off, I save the baseline and show it on the Gantt bar section so that one can see Planned vs Actual graphically.
What is the correct way to manage the programme if during the course of the project, additional tasks crop up and need to be added, as they might influence the critical path. If I add them in later, that menans they are not part of the original baseline and appear as blanks. Do I then select these "new" tasks and save the baseline again? I don’t want the original baseline finish to shift.
I hope what I am asking makes sense?
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?