Resource Usage

Tony LiveseyMember for 19 years 7 months
Created
2
2
0
In Resource Usage I show planned work for each resource by month so the Programme Manger can see future demands for each member of staff or resource type. I do this by rolling up to resource name level and setting the bottom tier timescale to Months

I am loading the resource profiles into our accounting system where the month of March is actually 19 Feb to 25 March but is called March. This is a problem because the March profile in my schedule (1st - 31st Mar) does not match the March profile in the finance system.

Is there a way to set the timescale up so that I can roll up the 5 weeks into a summary figure which is March?

2 replies

Oldest first
  1. 0
    James Griffiths ·
    Hi Tony,

    Welcome to PP.

    In MSP 2000, the short answer is NO.

    MSP is a scheduling programme, not an accounting programme. We have exactly the same issue, owing to the fact that we have accounting/finance periods of 5,4,4. Whether later versions are able to cope with this, I don’t know.

    HTH.

    James.
  2. 0
    Zhang Haixiang ·
    you can export your resource load to excel by day,
    then roll up in excel as you want
    then import to your fincal system