Critical Slack Calculation

John PflueglerMember for 19 years 5 months
Created
4
5
0
Hi,

I am detailing a shutdown schedule which entails a total duration of 1 day and includes over 150 tasks of varying lengths.

Is there any way to change the critical path slack to hours instead of days?

Thanks

John

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    John,
    MSP uses the same unit for the critical slack duration and the task duration; key in task duration in hours to get slack in hours on the gantt chart
    Alexandre
  2. 0
    Niek Zonneveld ·
    I think what John is referring to is the setting under [tools] [options] [calculation]: Task are critical if slack...

    I also think the answer is "No"

    HTH
  3. 0
    Vladimir Liberzon ·
    John,
    if you created resource-constrained schedule then total slacks showed by MS Project are wrong. So it does not make sense to pay attention to these data at all (days or hours - they are wrong in any case).
  4. 0
    Niek Zonneveld ·
    Yes you are right Vladimir, resource dependencies are just as important as precedence logic, and if you touch the levelling button in MSP, you can be sure that the task flag "critical" means next to nothing.

    Assuming John knows this, he could use a formula to drive one of the custom flag fields and then use that flag to mark a Gantt bar as critical based on hourly thresholds rather than the standard days.

    I’m out of my territory here but I think in a one-day plant shutdown resource constraints are of lesser concern.

Log in or join to reply