Graphical Indicators for Variances (Custom Task Field)

Stephen GradyMember for 23 years 2 months
Created
1
4
0
I’ve created a formula which I hoped would show a graphical indicator against the status of each task.

The formula I have used is:

IIf([% Complete]=100,"Task completed",IIf(ProjDateConv([Baseline Finish])="NA","Task not agreed",IIf(([Finish]-[Baseline Finish])<=20 And ([Finish]-[Baseline Finish])>7,"Task >1 week late",IIf(([Finish]-[Baseline Finish])>20,"Task >4 weeks late","Task on schedule"))))

The Graphical fields are:

equals "Task completed" x
equals "Task not agreed" Y
equals "Task on schedule" A
equals "Task >1 week late" B
equals "Task >4 weeks late"C

Obviously I have used symbols from the Image drop down box as opposed to X,Y,A,B & C.

The problem I have is that if a task has a greater varians than 20 days (4 weeks) there is nor graphical representation.

Can anyone advise.

Thanks

Steve

1 reply

Oldest first
  1. 0
    Brian Ultican ·
    First off there is an error in your formula so that it counts weekends into the number of days. Because of this a task that is only really only 19 working days late is shown by your formula to be 27 days late. I have made some adjustments below:
    IIf([% Complete]=100,"Task completed",IIf(ProjDateConv([Baseline Finish])="NA","Task not agreed",IIf((ProjDateDiff([Baseline Finish],[Finish],"Standard")/60/8)<=20 And (ProjDateDiff([Baseline Finish],[Finish],"Standard")/60/8)>7,"Task >1 week late",IIf((ProjDateDiff([Baseline Finish],[Finish],"Standard")/60/8)>20,"Task >4 weeks late","Task on schedule"))))

    As for your issue I cannot reproduce it. I get indicators as expected for all values.