Converting MSP 2003 into MSP 2007

Patrick van WeerdenburgMember for 21 years 4 months
Created
1
2
0
I’m currently implementing MSP 2007. What issues can I expect when converting MSP 2003 files into MSP 2007? Any suggestions or useful links would be great.

Thanks, Pat.

1 reply

Oldest first
  1. 0
    Paul Harris ·
    I found no problems in saving in 2003 but calendar named exceptions names in 2007 are not converted to 2003 and the name is lost on conversion but not the non work period

    When I updated my books to MSP 2007, I and some other people found a few issues with some of the more advanced features, such as Group resources and banding by Custom Fields was not working properly. This type of issue is normally fixed with the first service pack.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au

Log in or join to reply