Weightage ..?

Sivalingam PrabagaranMember for 19 years 1 month
Created
1
2
0

hi planners ..

ms project work programme based on duration (num of days)
sometime will never reflect the actual work at site ..

it there any possibility of adding a weightage to
all activities so that the act. will be represented
fairly ..?

thanks in advance ..

PS

1 reply

Oldest first
  1. 0
    L.E.N. Lewis ·
    The value for Duration is a derived number (it’s the difference between Start and Finish) so you can’t set up a formula to force it to something else.

    As a workaround, you could do this: Let’s assume that the duration is the product of two factors: Coats of paint (1, 2, or 3); and Number of Widgets. And let’s assume that these are *big* widgets and it takes a day to apply a coat of paint (which can dry overnight).

    So the duration for 10 widgets would be 10 days (if they get just 1 coat of paint), 20 days (if they get 2 coats) and 30 days (if they get three coats).

    Display the task columns Number1 and Number2. In column 1 put the number of coats of paint; in column 2 put the number of widgets.

    Display the column Duration1. Give it the formula:
    [Number1]*[Number2]*[Minutes Per Day]

    You need [Minutes Per Day] because project stores durations in minutes.

    Finally, you need to move "Duration1" into "Duration" and for that you’ll need a little VBA:


    sub DurationOverride()

    dim tsk as Task
    for each tsk in activeproject.tasks
    If not tsk is nothing then ’ignore blank lines
    if not tsk.summary then ’ignore summary tasks
    if tsk.duration1 > 0 then ’update tasks that have a calculated value
    tsk.duration = tsk.duration1
    end if
    end if
    end if
    next

    Note that if you have tasks with a FNLT, FNET, MFO Constraint type then the Start Date will move to an earlier date (the Finish date is locked and won’t move).

    Note that if you have predecessors/successors on the task where you have calculated the Duration then Project will impose those constraints on the task Start/Finish as well.