Problem with dates...
In the Open Standard
Maya CMember for 19 years 4 months
- Created
- 4
- 3
0
I am having trouble holding an activity in place.
I have an activity (Fixed units)that had a START of 9/4/07 and FINISH of 9/24/07. I was told that the activity has already started on 8/15/07, but will be done on 9/24/07. So I want to be able to actualize the Start on 8/15/07 and put an EXPECTED FINISH (P3e terminology) to keep the activity in place as ending on 9/24.
With Project I cannot do this. It is messing the dates up. The activity still shows 0% Complete. I am not sure what is causing this.
IS there a way to put an expected finish to hold it in place after starting it?
Thanks.
I have an activity (Fixed units)that had a START of 9/4/07 and FINISH of 9/24/07. I was told that the activity has already started on 8/15/07, but will be done on 9/24/07. So I want to be able to actualize the Start on 8/15/07 and put an EXPECTED FINISH (P3e terminology) to keep the activity in place as ending on 9/24.
With Project I cannot do this. It is messing the dates up. The activity still shows 0% Complete. I am not sure what is causing this.
IS there a way to put an expected finish to hold it in place after starting it?
Thanks.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?