Sorting tasks: some challenge there is !

Nicolas IgersheimMember for 19 years 3 months
Created
1
2
0
Hi all,

I have this model programme featuring typical
tasks and relations.
Unfortunately, tasks are sorted, and subsequently
numbered, according to ressource and not to logic
ie chronology.

I tried to create a new file copying
the tasks after sorting them according
to start date, thus relating number and chronology,
but unfortunately, when I do that,
the successors and predecessors numbers
refer to the copied tasks old numbers
and not the new pasted ones!

Any suggestion out there please?

1 reply

Oldest first
  1. 0
    Nicolas Igersheim ·
    Well I should have looked
    before I asked.
    In the dialog box for Project Sort,
    there is a check for
    renumber all activities,
    It seems to answer my problem all right.

    Thanks anyway! ;-)