Criticality

Stuart AtkinsonMember for 22 years 9 months
Created
1
2
0
I have been handed a MSP 2000 file and when I use the filter to show ’critical’ it highlights all the critical items names in blue. The trouble is it leaves the non-critical items in view (normal text colour).

Help much appreciated

1 reply

Oldest first
  1. 0
    Trevor Rabey ·
    Perhaps someone has changed the Filter to a Highlight Filter before you got it.
    You can see this if you go to Project, Filtered For, More Filters, Edit. See the checkbox.
    If you want to recover the original (you should) you can use Tools, Organiser to get it back from the Global template.