Some tasks on my fully linked programme show zero ’total slack’. One must assume that any delay to these tasks would result in a corresponding delay to the end date. In some instances it does not - WHY?

Thanks,

Stuart

1 reply

Oldest first
  1. 0
    Niek Zonneveld ·
    If you use constraints or deadlines in your schedule that doesn’t have to be the case.

    H.T.H.