producing specific role resouces report
In the Open Standard
EV
Emmanuel ValMember for 18 years 11 months
- Created
- 18
- 5
0
18 replies
Oldest first- 0EVEmmanuel Val ·Okay,
I used "role" to mean a the grouping of the resources. one of the roles in Resources will be Project managers another role will be Business Analysts, other role will be IT Supports etc.
I am trying to generate a report of say the BA. I am trying to capture when all the named BAs are allocated to projects and when they are not.
Emmanuel - 0AFAlexandre Faulx-Briole ·OK,
I would use the Group column to display the "role" of each resource; then use the dynamic filter "resource Groups..." to be able to select a specific role from all the roles; and export this filtered list to MS Excel.
Dynamic filters are the ones with a question mark
Alexandre - 0AFAlexandre Faulx-Briole ·Hi Emmanuel,
you cannot use filters with analyse timescaled data; just select the taks BEFORE you launch the process, and click "Selected tasks"
should you prefer to Export the data (File, Save As), select the filter you need in the step Tasks mapping (step #6 if you follow the whole process) in the Export Assistant.
Alexandre - 0EVEmmanuel Val ·Alexandre
I was not using the analyse timescale in Excel.
I wanted to using filters to generate the project or in in Gantt chart (task name), the name of the resources, a monthly view of the assigments, avaliable from and hours avaliable views.
When I try to use the filters (resources filters), there are conflicts (the test value can not be used with the field for the data) resolution.
Emmanuel - 0EVEmmanuel Val ·Hi Alexandre
Okay, on the MSP that I am using, it is just one major project with many different clients and tasks for these client. The way the resources are grouped is a selection of 2 PMs, 3-7 BAs, 5-20 Technical staffs for each different task.
What I am looking to produce is a report with all the projects (tasks) with all BAs (the names of this BAs), a monthly view of their assignments, when these assignments finishes, which will be when they are available from and how many hours they are assigned on each Projects (tasks).
This is basically way I am trying to report but I guess I am not knowledgeable enough to use the filter on MSP to produce such view or report. Emmanuel
- 0AFAlexandre Faulx-Briole ·OK,
you rather should use Project, Group By, and group the project’s tasks by resources groups (BA, ...)
then select the appropriate table from View, Tables, and maybe fields by editing the Table (View, Tables, More tables)
then, insert a page break after each group
and print