Specific VBA code for exporting data to Excel

Andrew OwensonMember for 20 years 11 months
Created
5
5
0
Guys

I have a procurement programme in MSP which I have linked to an excel file. I have a planned, actual an forecast date for each activity, and about 15 activities per package. I have a reference programme with 115 packages. I then copy and rename to suit a new project. The problem I have is that the excel file is extremely slow and the connections seem fragile to say the least. Is there anyone out there who can give me a specific code to export the baseline, actual and current date to a specific cell in excel. I know absolutely nothing about Visual basic, and I am following up a previous thread in which I was given various places to look up, but did not give me the answer I am looking for. It does not have to necessarily export to excel, but produce a report which gives the package on the left with the planned actual and forecast dates for each activity in a spreadsheet fashion.

Thankyou in advance - a frustrated planner

5 replies

Oldest first
  1. 0
    Hannes de Bruyne ·
    Hi, maybe I can help you with a small Macro:

    you must create an Excel-sheet with following sheets:Activity, WBS-Dictionary, Resource, Filters, Calendar, Activity-Code and CDI.

    Then create a Macro Extras->Macro->Visual Basic Editor and copy Macro-Text into this window.


    This Macro will transform files from MS-Project to Excel.
    It is based on VBA-language of MS-Excel and MS-Project. Therefore it is neccesary that the references are all loaded.

    The ActiveX-Element of Microsoft Project must be activated : Extras -> Macros -> Visual Basic Editor. Ater that in the menu of the Visual Basic Editor: Extras -> References -> "Microsoft Project 10.0 Object Library"


    Have fun and just ask questions


    Option Explicit

    Dim MSProj, ProjAppl As Object
    Dim A As Assignment

    Dim strName, TaskName, TaskSuccessor, Title, Test, Zwischen, Text1, Text2, Text3, Text4, Text5, Number1, Number2, Date1, Date2 As String
    Dim n As Long
    Dim bRet, Down, DoOff, FrOff, SaOff, SoOff As Boolean
    Dim iColumn, iEmpty, DayWk, StartYear, FinishYear As Integer
    Dim Cal As Calendar
    Dim Fil As Filter
    Dim CalRange, ResRange As Range
    Dim aProj As Project

    Dim MsgBoxRet As VbMsgBoxResult

    ’Primavera P3
    Dim Pos1, Pos2, Pos3, Pos4, FieldValue As Long
    ’Dim ActRecord As Variant
    Dim UserName, Password, ProjectName, SuccHelp, WBSstring, fname, ResString As String
    Dim iRow, i, j, k, l, temp, WBS(1 To 7), LastLevel, CutOff, PredRow, findRow, ConstraintType, MoreHol As Integer
    Dim Session, P3Proj, Act, Log, WBSVal, Succ, Res, CostAcc, P3Cal, P3GloCal, ResCal, ProjAbstr, ResAssign As Object
    Dim HoDay, Level, ResPrice, ResLimit, ACodes, CodeVal, CDI, P3Filter, First, Last As Object

    Private Sub ReadMSPjroject(Action As Integer)

    ’*** Open MS-Project File ***

    Set MSProj = CreateObject("MSProject.Project")
    Set ProjAppl = MSProj.Application

    Title = "Please Select Microsoft Project File"
    fname = Application.GetOpenFilename("Microsoft Project Files (*.mpp), *.mpp", , Title)

    ProjAppl.FileOpen fname, ReadOnly:=False, FormatID:="MSProject.MPP"
    Set aProj = ProjAppl.ActiveProject
    strName = aProj.Name
    Application.DisplayStatusBar = True
    OptionsEdit DayLabelDisplay:=1

    ’**************************** RESOURCES *********************************

    Application.DisplayStatusBar = True
    Application.StatusBar = "Reading Resources..."
    Worksheets("Resource").Activate
    Cells.Select
    Selection.ClearContents

    Range(Cells(2, 1), Cells(2, 14)) = Array("Nr:", "Name", "MaterialLabel", "MaxUnits", "Type", "Initials", "Rate", "OvertimeRate", "Calendar", "Assignments", "Availabilities", "AvailableFrom", "AvailableTo", "Group")
    Cells(2, 11) = "Number of"
    Cells(2, 12) = "Limits"

    iRow = 3
    For i = 1 To aProj.Resources.Count
    Cells(iRow, 1) = i
    Cells(iRow, 2) = aProj.Resources(i).Name
    Cells(iRow, 3) = aProj.Resources(i).MaterialLabel
    Cells(iRow, 4) = aProj.Resources(i).MaxUnits
    Cells(iRow, 5) = aProj.Resources(i).Type
    Cells(iRow, 6) = aProj.Resources(i).Initials
    Cells(iRow, 7) = aProj.Resources(i).StandardRate
    If Cells(iRow, 7) <> "" Then
    l = Len(Cells(iRow, 7).Text)
    ’Pos1 = InStr(1, Cells(iRow, 7).Text, "Std")
    Pos2 = InStr(1, Cells(iRow, 7).Text, ",")
    Cells(iRow, 7) = Left(Cells(iRow, 7), Pos2 + 2) * 8 ’IIf(Pos1 > 0, 8, 1)
    End If

    Cells(iRow, 8) = aProj.Resources(i).OvertimeRate
    If Cells(iRow, 8) <> "" Then
    l = Len(Cells(iRow, 8).Text)
    ’Pos1 = InStr(1, Cells(iRow, 8).Text, "Std")
    Pos2 = InStr(1, Cells(iRow, 8).Text, ",")
    Cells(iRow, 8) = Left(Cells(iRow, 8), Pos2 + 2) * 8 ’IIf(Pos1 > 0, 8, 1)
    End If
    Cells(iRow, 9) = aProj.Resources(i).BaseCalendar

    Cells(iRow, 12) = aProj.Resources(i).AvailableFrom
    Cells(iRow, 13) = aProj.Resources(i).AvailableTo
    Cells(iRow, 14) = aProj.Resources(i).Group

    iRow = iRow + 1
    Next i

    ’*************************** FILTERS ***************************

    Application.StatusBar = "Reading Filters..."
    Worksheets("Filters").Activate
    Cells.Select
    Selection.ClearContents
    Cells(1, 2) = "CurrentFilter:"
    Cells(1, 3) = aProj.CurrentFilter

    Range(Cells(2, 2), Cells(2, 9)) = Array("Nr", "Name", "FilterType", "Application", "Index", "Parent", "ShowInMenu", "ShowRelatedSummaryRows")

    iRow = 3
    For i = 1 To aProj.TaskFilters.Count
    Cells(iRow, 2) = IIf(i > 1, i + 1, i)
    Cells(iRow, 3) = aProj.TaskFilters(i).Name
    If Cells(iRow, 3) = Cells(1, 3) Then Cells(1, 4) = Cells(iRow, 2)
    temp = aProj.TaskFilters(i).FilterType
    Select Case temp
    Case 0
    Cells(iRow, 4) = "TaskItem"
    Case 1
    Cells(iRow, 4) = "ResItem"
    Case 2
    Cells(iRow, 4) = "Other"
    End Select
    Cells(iRow, 5) = aProj.TaskFilters(i).Application
    Cells(iRow, 6) = aProj.TaskFilters(i).Index
    Cells(iRow, 7) = aProj.TaskFilters(i).Parent
    Cells(iRow, 8) = aProj.TaskFilters(i).ShowInMenu
    Cells(iRow, 9) = aProj.TaskFilters(i).ShowRelatedSummaryRows
    iRow = iRow + 1
    Next i

    ’************************** CALENDARS ************************************

    Application.StatusBar = "Reading Calendars..."
    Worksheets("Calendar").Activate
    Cells.Select
    Selection.ClearContents
    Range(Cells(2, 1), Cells(2, 13)) = Array("Name", "MS-CalId", "P3-CalId", "So", "Mo", "Di", "Mi", "Do", "Fr", "Sa", "Days/Wk", "Number of", "Holidays")
    Range(Cells(3, 1), Cells(3, 12)) = Array("Global", 0, 0, True, True, True, True, True, True, True, 7, 0)
    iEmpty = 0
    For i = 1 To aProj.BaseCalendars.Count
    Application.StatusBar = "Reading Calendar " & i
    If aProj.BaseCalendars(i).Name = (aProj.Calendar) Then
    iRow = 4
    iEmpty = iEmpty + 1
    Else
    iRow = i + 4 - iEmpty
    End If
    Cells(iRow, 1) = aProj.BaseCalendars(i).Name
    Cells(iRow, 2) = aProj.BaseCalendars(i).Index
    Cells(iRow, 3) = iRow - 3
    Cells(iRow, 4) = aProj.BaseCalendars(i).WeekDays(1).Working ’So
    Cells(iRow, 5) = aProj.BaseCalendars(i).WeekDays(2).Working ’Mo
    Cells(iRow, 6) = aProj.BaseCalendars(i).WeekDays(3).Working
    Cells(iRow, 7) = aProj.BaseCalendars(i).WeekDays(4).Working
    Cells(iRow, 8) = aProj.BaseCalendars(i).WeekDays(5).Working
    Cells(iRow, 9) = aProj.BaseCalendars(i).WeekDays(6).Working ’Fr
    Cells(iRow, 10) = aProj.BaseCalendars(i).WeekDays(7).Working ’Sa

    l = 0

    For j = 1 To (aProj.BaseCalendars(i).Period(aProj.ProjectStart, aProj.ProjectFinish))
    SoOff = (Weekday(CDate(aProj.ProjectStart) + j) = 1 And Cells(iRow, 4) = False)
    DoOff = (Weekday(CDate(aProj.ProjectStart) + j) = 5 And Cells(iRow, 8) = False)
    FrOff = (Weekday(CDate(aProj.ProjectStart) + j) = 6 And Cells(iRow, 9) = False)
    SaOff = (Weekday(CDate(aProj.ProjectStart) + j) = 7 And Cells(iRow, 10) = False)
    If Not SoOff And Not SaOff Then ’And Not FrOff
    If aProj.BaseCalendars(i).Period(CDate(aProj.ProjectStart) + j).Working = False Then
    Cells(iRow, 13 + l) = (CDate(aProj.ProjectStart) + j)
    l = l + 1
    End If
    End If
    Next j
    Cells(iRow, 11) = 7 - IIf(Cells(iRow, 4), 0, 1) - IIf(Cells(iRow, 5), 0, 1) + IIf(Cells(iRow, 6), 0, 1) - IIf(Cells(iRow, 7), 0, 1) - IIf(Cells(iRow, 8), 0, 1) - IIf(Cells(iRow, 9), 0, 1) - IIf(Cells(iRow, 10), 0, 1)
    Cells(iRow, 12) = l

    Next i

    ’************************** WBS-DICTIONARY ************************************

    Worksheets("WBS-Dictionary").Activate
    Cells.Select
    Selection.ClearContents
    Cells(2, 1) = "Level"
    Cells(2, 2) = "Value"
    Cells(2, 3) = "Description"

    ’************************** CUSTOM DATA ITEMS ************************************

    Application.StatusBar = "Reading Custom Data Items..."
    Worksheets("CDI").Activate
    Cells.Select
    Selection.ClearContents
    Range(Cells(2, 2), Cells(2, 5)) = Array("Description", "Length", "Name", "Type")

    iRow = 3
    On Error Resume Next
    If (CustomFieldGetName(pjCustomTaskNumber1)) <> "" Then
    Cells(iRow, 1) = "Number1"
    Cells(iRow, 2) = (CustomFieldGetName(pjCustomTaskNumber1))
    Number1 = (CustomFieldGetName(pjCustomTaskNumber1))
    ’Cells(iRow, 3) = 1
    Cells(iRow, 4) = "Nr1"
    Cells(iRow, 5) = "N"
    ’ For i = 1 To 100
    ’ Cells(iRow, 4 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i)
    ’ If Cells(iRow, 4 + i * 2) = "" Then Exit For
    ’ Cells(iRow, 3) = IIf(Len(CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i)) > Cells(iRow, 3), Len((CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i))), Cells(iRow, 3))
    ’ Cells(iRow, 5 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListDescription, i)
    ’ Cells(iRow, 5) = i
    ’ Next i
    iRow = iRow + 1
    End If

    If (CustomFieldGetName(pjCustomTaskNumber2)) <> "" Then
    Cells(iRow, 1) = "Number2"
    Cells(iRow, 2) = (CustomFieldGetName(pjCustomTaskNumber2))
    Number2 = (CustomFieldGetName(pjCustomTaskNumber2))
    ’Cells(iRow, 3) = 1
    Cells(iRow, 4) = "Nr2"
    Cells(iRow, 5) = "N"
    ’For i = 1 To 100
    ’ Cells(iRow, 4 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i)
    ’ If Cells(iRow, 4 + i * 2) = "" Then Exit For
    ’ Cells(iRow, 3) = IIf(Len(CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i)) > Cells(iRow, 3), Len((CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i))), Cells(iRow, 3))
    ’ Cells(iRow, 5 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListDescription, i)
    ’ Cells(iRow, 5) = i
    ’Next i
    iRow = iRow + 1
    End If

    If (CustomFieldGetName(pjCustomTaskDate1)) <> "" Then
    Cells(iRow, 1) = "Date1"
    Cells(iRow, 2) = (CustomFieldGetName(pjCustomTaskDate1))
    Date1 = (CustomFieldGetName(pjCustomTaskDate1))
    ’Cells(iRow, 3) = 1
    Cells(iRow, 4) = "Dat1"
    Cells(iRow, 5) = "S"
    ’ For i = 1 To 100
    ’ Cells(iRow, 4 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i)
    ’ If Cells(iRow, 4 + i * 2) = "" Then Exit For
    ’ Cells(iRow, 3) = IIf(Len(CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i)) > Cells(iRow, 3), Len((CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i))), Cells(iRow, 3))
    ’ Cells(iRow, 5 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListDescription, i)
    ’ Cells(iRow, 5) = i
    ’ Next i
    iRow = iRow + 1
    End If

    If (CustomFieldGetName(pjCustomTaskDate2)) <> "" Then
    Cells(iRow, 1) = "Dat2"
    Cells(iRow, 2) = (CustomFieldGetName(pjCustomTaskDate2))
    Date2 = (CustomFieldGetName(pjCustomTaskDate2))
    ’Cells(iRow, 3) = 1
    Cells(iRow, 4) = "Date2"
    Cells(iRow, 5) = "S"
    ’ For i = 1 To 100
    ’ Cells(iRow, 4 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i)
    ’ If Cells(iRow, 4 + i * 2) = "" Then Exit For
    ’ Cells(iRow, 3) = IIf(Len(CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i)) > Cells(iRow, 3), Len((CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListValue, i))), Cells(iRow, 3))
    ’ Cells(iRow, 5 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskNumber1, pjValueListDescription, i)
    ’ Cells(iRow, 5) = i
    ’ Next i
    End If

    ’****************************** ACTIVITY-CODE *************************************

    Worksheets("Activity-Code").Activate
    Cells.Select
    Selection.ClearContents
    Range(Cells(2, 2), Cells(2, 6)) = Array("Description", "Length", "Name", "Number of", "Values")

    iRow = 3
    If (CustomFieldGetName(pjCustomTaskText1)) <> "" Then
    Cells(iRow, 1) = "Text1"
    Cells(iRow, 2) = (CustomFieldGetName(pjCustomTaskText1))
    Text1 = (CustomFieldGetName(pjCustomTaskText1))
    Cells(iRow, 3) = 1
    Cells(iRow, 4) = "TXT1"
    For i = 1 To 1000
    Cells(iRow, 4 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText1, pjValueListValue, i)
    If Cells(iRow, 4 + i * 2) = "" Then Exit For
    Cells(iRow, 3) = IIf(Len(CustomFieldValueListGetItem(pjCustomTaskText1, pjValueListValue, i)) > Cells(iRow, 3), Len((CustomFieldValueListGetItem(pjCustomTaskText1, pjValueListValue, i))), Cells(iRow, 3))
    Cells(iRow, 5 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText1, pjValueListDescription, i)
    Cells(iRow, 5) = i
    Next i
    iRow = iRow + 1
    End If

    If (CustomFieldGetName(pjCustomTaskText2)) <> "" Then
    Cells(iRow, 1) = "Text2"
    Cells(iRow, 2) = (CustomFieldGetName(pjCustomTaskText2))
    Text2 = (CustomFieldGetName(pjCustomTaskText2))
    Cells(iRow, 3) = 1
    Cells(iRow, 4) = "TXT2"

    For i = 1 To 1000
    Cells(iRow, 4 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText2, pjValueListValue, i)
    If Cells(iRow, 4 + i * 2) = "" Then Exit For
    Cells(iRow, 3) = IIf(Len(CustomFieldValueListGetItem(pjCustomTaskText2, pjValueListValue, i)) > Cells(iRow, 3), Len((CustomFieldValueListGetItem(pjCustomTaskText2, pjValueListValue, i))), Cells(iRow, 3))
    Cells(iRow, 5 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText2, pjValueListDescription, i)
    Cells(iRow, 5) = i
    Next i
    iRow = iRow + 1
    End If

    If (CustomFieldGetName(pjCustomTaskText3)) <> "" Then
    Cells(iRow, 1) = "Text3"
    Cells(iRow, 2) = (CustomFieldGetName(pjCustomTaskText3))
    Text3 = (CustomFieldGetName(pjCustomTaskText3))
    Cells(iRow, 3) = 1
    Cells(iRow, 4) = "TXT3"
    Cells(iRow, 5) = 0
    For i = 1 To 1000
    Cells(iRow, 4 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText3, pjValueListValue, i)
    If Cells(iRow, 4 + i * 2) = "" Then Exit For
    Cells(iRow, 3) = IIf(Len(CustomFieldValueListGetItem(pjCustomTaskText3, pjValueListValue, i)) > Cells(iRow, 3), Len((CustomFieldValueListGetItem(pjCustomTaskText3, pjValueListValue, i))), Cells(iRow, 3))
    Cells(iRow, 5 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText3, pjValueListDescription, i)
    Cells(iRow, 5) = i
    Next i
    iRow = iRow + 1
    End If

    If (CustomFieldGetName(pjCustomTaskText4)) <> "" Then
    Cells(iRow, 1) = "Text4"
    Cells(iRow, 2) = (CustomFieldGetName(pjCustomTaskText4))
    Text4 = (CustomFieldGetName(pjCustomTaskText4))
    Cells(iRow, 3) = 1
    Cells(iRow, 4) = "TXT4"
    Cells(iRow, 5) = 0
    For i = 1 To 1000
    Cells(iRow, 4 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText4, pjValueListValue, i)
    If Cells(iRow, 4 + i * 2) = "" Then Exit For
    Cells(iRow, 3) = IIf(Len(CustomFieldValueListGetItem(pjCustomTaskText4, pjValueListValue, i)) > Cells(iRow, 3), Len((CustomFieldValueListGetItem(pjCustomTaskText4, pjValueListValue, i))), Cells(iRow, 3))
    Cells(iRow, 5 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText4, pjValueListDescription, i)
    Cells(iRow, 5) = i
    Next i
    iRow = iRow + 1
    End If

    If (CustomFieldGetName(pjCustomTaskText5)) <> "" Then
    Cells(iRow, 1) = "Text5"
    Cells(iRow, 2) = (CustomFieldGetName(pjCustomTaskText5))
    Text5 = (CustomFieldGetName(pjCustomTaskText5))
    Cells(iRow, 3) = 1
    Cells(iRow, 4) = "TXT5"
    Cells(iRow, 5) = 0
    For i = 1 To 1000
    Cells(iRow, 4 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText5, pjValueListValue, i)
    If Cells(iRow, 4 + i * 2) = "" Then Exit For
    Cells(iRow, 3) = IIf(Len(CustomFieldValueListGetItem(pjCustomTaskText5, pjValueListValue, i)) > Cells(iRow, 3), Len((CustomFieldValueListGetItem(pjCustomTaskText5, pjValueListValue, i))), Cells(iRow, 3))
    Cells(iRow, 5 + i * 2) = CustomFieldValueListGetItem(pjCustomTaskText5, pjValueListDescription, i)
    Cells(iRow, 5) = i
    Next i
    End If

    ’****************************** ACTIVITIES ***************************************

    Worksheets("Activity").Activate
    Cells.Select
    Selection.ClearContents

    Cells(1, 1) = "Activity"
    Cells(1, 5) = "Links"
    Cells(1, 8) = "Headers"
    Cells(1, 13) = "Constraints"
    Cells(1, 15) = "Early Dates"
    Cells(1, 17) = "Actual Dates"
    Cells(1, 19) = "ProjStart:"
    Cells(1, 20) = aProj.ProjectStart
    Cells(1, 21) = "ProjFinish:"
    Cells(1, 22) = aProj.ProjectFinish
    Cells(1, 23) = "StatusDate:"
    Cells(1, 24) = aProj.StatusDate
    Cells(1, 25) = "Version:"
    Cells(1, 26) = aProj.VersionName
    Cells(1, 27) = "Digits:"
    Cells(1, 28) = aProj.CurrencyDigits
    Cells(1, 29) = "StartWeekOn:"
    Cells(1, 30) = aProj.StartWeekOn
    Cells(1, 31) = "Revision."
    Cells(1, 32) = aProj.RevisionNumber
    Cells(1, 33) = "Print Date:"
    Cells(1, 34) = aProj.LastPrintedDate

    Range(Cells(2, 1), Cells(2, 8)) = Array("ID", "UniqueID", "Name", "OD", "Number of", "Successors", "Milestone", "Summary")
    Range(Cells(2, 9), Cells(2, 15)) = Array("Number", "Level", "WBS", "Note", "Date", "Type", "Early Start")
    Range(Cells(2, 16), Cells(2, 20)) = Array("Early Finish", "Actual Start", "Actual Finish", "Perc. Compl.", "Calendar")
    Range(Cells(2, 21), Cells(2, 29)) = Array(Text1, Text2, Text3, Text4, Text5, Number1, Number2, Date1, Date2)
    Cells(2, 30) = "Resources"

    j = 1
    WBS(1) = WBS(2) = WBS(3) = WBS(4) = WBS(5) = WBS(6) = WBS(7) = 1
    temp = 1
    iEmpty = 0
    LastLevel = 0

    For i = 1 To aProj.Tasks.Count
    Application.StatusBar = "Reading activity " & i & " of " & aProj.Tasks.Count
    If Not aProj.Tasks(i) Is Nothing Then

    iRow = i + 2 - iEmpty

    Cells(iRow, 1) = aProj.Tasks(i).ID
    ’Cells(iRow, 2) = aProj.Tasks(i).UniqueID
    Cells(iRow, 3) = aProj.Tasks(i).Name
    Cells(iRow, 4) = aProj.Tasks(i).Duration / (aProj.HoursPerDay * 60)
    Cells(iRow, 5) = aProj.Tasks(i).SuccessorTasks.Count
    Cells(iRow, 6) = aProj.Tasks(i).Successors
    Cells(iRow, 7) = aProj.Tasks(i).Milestone
    Cells(iRow, 8) = aProj.Tasks(i).Summary

    ’**************************** Activity.WBS-Assignment *****************************

    WBSstring = ""

    If aProj.Tasks(i).OutlineLevel = LastLevel Then
    WBS(aProj.Tasks(i).OutlineLevel) = WBS(aProj.Tasks(i).OutlineLevel) + 1
    Else
    If aProj.Tasks(i).OutlineLevel > LastLevel Then
    WBS(aProj.Tasks(i).OutlineLevel) = 1
    Down = False
    ElseIf aProj.Tasks(i).OutlineLevel < LastLevel Then
    WBS(aProj.Tasks(i).OutlineLevel) = WBS(aProj.Tasks(i).OutlineLevel) + 1
    Down = True
    End If
    End If


    For l = 1 To aProj.Tasks(i).OutlineLevel
    WBSstring = WBSstring & IIf(WBS(l) < 10, "0" & WBS(l), WBS(l))
    Next l

    If aProj.Tasks(i).Summary = True Or aProj.Tasks(i).OutlineLevel = 1 Or (aProj.Tasks(i).OutlineLevel < LastLevel And WBS(aProj.Tasks(i).OutlineLevel) > 1) Or (aProj.Tasks(i).OutlineLevel = LastLevel And Down = True) Then
    Worksheets("WBS-Dictionary").Cells(j + 2, 1) = aProj.Tasks(i).OutlineLevel
    Worksheets("WBS-Dictionary").Cells(j + 2, 2) = WBSstring
    Worksheets("WBS-Dictionary").Cells(j + 2, 3) = aProj.Tasks(i).Name
    j = j + 1
    Else
    WBSstring = Left(WBSstring, Len(WBSstring) - 2)
    End If
    LastLevel = aProj.Tasks(i).OutlineLevel
    If aProj.Tasks(i).OutlineLevel > Worksheets("WBS-Dictionary").Cells(1, 1) Then
    Worksheets("WBS-Dictionary").Cells(1, 1) = aProj.Tasks(i).OutlineLevel
    End If
    Worksheets("Activity").Activate
    Cells(iRow, 9) = aProj.Tasks(i).OutlineNumber
    Cells(iRow, 10) = aProj.Tasks(i).OutlineLevel
    Cells(iRow, 11) = WBSstring

    ’**************************************************************************************

    Cells(iRow, 12) = aProj.Tasks(i).Notes
    Cells(iRow, 13) = aProj.Tasks(i).ConstraintDate
    Cells(iRow, 14) = aProj.Tasks(i).ConstraintType
    Cells(iRow, 15) = aProj.Tasks(i).EarlyStart
    Cells(iRow, 16) = aProj.Tasks(i).EarlyFinish
    Cells(iRow, 17) = aProj.Tasks(i).ActualStart
    Cells(iRow, 18) = aProj.Tasks(i).ActualFinish
    Cells(iRow, 19) = aProj.Tasks(i).PercentComplete
    Cells(iRow, 20) = aProj.Tasks(i).Calendar
    Cells(iRow, 21) = aProj.Tasks(i).Text1
    Cells(iRow, 22) = aProj.Tasks(i).Text2
    Cells(iRow, 23) = aProj.Tasks(i).Text3
    Cells(iRow, 24) = aProj.Tasks(i).Text4
    Cells(iRow, 25) = aProj.Tasks(i).Text5
    Cells(iRow, 26) = aProj.Tasks(i).Number1
    Cells(iRow, 27) = aProj.Tasks(i).Number2
    Cells(iRow, 28) = aProj.Tasks(i).Date1
    Cells(iRow, 29) = aProj.Tasks(i).Date2


    ’********************* ACTIVITY.RESOURCE ASSIGNMENTS ******************

    Set ResRange = Worksheets("Resource").Range(Worksheets("Resource").Cells(3, 2), Worksheets("Resource").Cells(202, 13))
    iColumn = 31
    For Each A In aProj.Tasks(i).Assignments
    Cells(iRow, iColumn) = A.ResourceName

    ’Cells(iRow, iColumn) = Application.WorksheetFunction.VLookup(Cells(iRow, iColumn), Worksheets("Resource").Range("ResRange"), 5)


    If A.ResourceType = 0 Then
    Cells(iRow, iColumn + 1) = A.Units * Cells(iRow, 4)
    Else
    Cells(iRow, iColumn + 1) = A.Units
    End If
    iColumn = iColumn + 4 ’35,39,43
    Next A
    Cells(iRow, 30) = (iColumn - 31) / 4
    Else
    iEmpty = iEmpty + 1
    End If
    Next i
    Exit Function

    NoFileOpen:
    ’MsgBox MSG_NOFILEOPEN, vbExclamation + R_TO_L, Title:=Application.Name
    End ’Makro beenden.

    End Sub
  2. 0
    Andrew Owenson ·
    Hannes

    Thankyou very much for your "small" macro. I will give it a go and will probably have to get back to you as I know absolutely nothing about macros.

    Many regards

    Andrew
  3. 0
    Hannes de Bruyne ·
    Hi Andrew,

    I just did, what you have done. Due to extracting this macro from a large program an error occured -> the first line after the declaration part should read:


    Private Sub ReadMSPjroject()

    instead of

    Private Sub ReadMSPjroject(Action As Integer)




    I prepared the extracted macro in an separate Excel-file now and tested it - just send yr e-mail address, I will send you the file.

    Requests from other persons welcome as well.
  4. 0
    John Smitt ·
    any chance of a how to, Ive not tried to write a macro so have tried and failed - even with the fix.
  5. 0
    Hannes de Bruyne ·
    Hi,

    as allready said, send me a mail and I will send you the file with the macro .or. write down the error message / problem, and I will try to give you the answer. You can send the mail to:
    Hannes.de-Bruyne@hochtief.de

    Hannes