Hi All
Can someone help me for writing a macro
for hiding all task bars
Thanks

4 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    Hemanth,
    This module removes all the bars for selected tasks:

    *****************************************
    Sub Hide_bars()

    Dim t As Task

    For Each t In ActiveSelection.Tasks

    t.HideBar = YES

    Next t

    End Sub
    ******************************************

    This is a very simple example. You’ll need to write error handling around it to make it robust.

    H.T.H.

    Niek.
  2. 0
    James Griffiths ·
    There is no need to write a macro. Just highlight all the activities, click on the Task Information icon,General tab and then tick the "Hide Task Bar" box.

    HTH.

    James.
  3. 0
    Hemanth Kumar ·
    Thank You Niek
    Dear James

    My Project if not opened without enabling macros will be shown as a dis organised crap without any bars

    So The viewer has to enable macro to view it. which will trigger a series of other macros which prevent edit,,print,, save,, show copy right informations etc etc

    i dont want somebody even my client copy my plan and reuse it



  4. 0
    Niek Zonneveld ·
    My pleasure Hemanth,

    If you always want to apply this for the entire project you should replace "ActiveSelection.Tasks" by "ActiveProject.Tasks" in the code I’ve sent you earlier.

    H.T.H.

    Niek.