Skip to content

Percent Work and Percent Complete

Moutaz AldeibMember for 22 years 9 months
Created
3
4
0
Dear Planners,

Could any one tell me the difference in MS Project between % work and % complete and which one should be used to update the program.

Regards,

Moutaz

3 replies

Oldest first
  1. 0
    Imran Arshad ·
    %age complete is used to update progress
  2. 0
    Trevor Rabey ·
    Moutaz,

    A % of anything must be a number with a numerator and denominator.

    There is no such thing as "% Progress", unless there is a numerator and a denominator.

    % Complete measures how much of the Task Actual Duration has elapsed as a fraction of the Total Duration.

    % Complete (Duration) = (Actual Duration)/(Total Duration)

    Similarly,
    % Work Complete = (Actual Work)/(Total Work)

    Do your updates with the Tracking Gantt and the Tracking Table and the Tracking Toolbar.
    Type in Actual Start, Actual Finish, Actual Duration, Remaining Duration. Do not type in % Complete because MSP will calculate this for you.
  3. 0
    Alexandre Faulx-Briole ·
    Moutaz,
    do you want MS Project to calculate how much resources have worked since the beginning of the activity after you enter the activity actual duration or % Complete?
    then do not change anything in the setup and let MS Proejct calculate the % Work Complete from the % (Duration) Complete
    on th eother hand, should you need to disociate actual work from actual duration, do the following:
    Tools, Options, Calculation, then clear the 1st option under "Calculation options for (X) project" (sorry, I am using MSP in French), something like "Update tasks => update resources"
    MSP will no longer calculate the %work complete, and you will be able to enter the value by yourself without having MSP to calculate the other side of it
    Hope this helps,
    Alexandre

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?