2007 Earned Value Bug

Trevor JordanMember for 18 years 8 months
Created
2
2
0
Hi Everyone,
Just wondering if anybody else is experiencing problems using the ’Task Earned Value Over Time’functionality to produce EV Pivot Tables and Graphs. The data in the AC field is incorrect while PV and EV fields have no data.

No problems with the same data in 2003.

Best Regards,

Trevor

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Trevor,
    I did: same problem with MS Project 2007 Std French edition
    Alexandre
  2. 0
    Trevor Jordan ·
    Hi Alexandre,
    Thanks for your reply.
    I have done some investigation and I have found out the excact field which is corrupted. In the table ’Cost’ the field ’Total Cost’ is being calcultated incorrectly. This is why we cannot use Visual Reports to generate a graph and pivot table.

    But having said that all other table fields are correct. I refer to the fields in the following tables:
    1. Earned Value
    2. Earned Value Cost Inidcators
    3. Earned Value Scheduling Indicators

    This can be proven by going to the ’Task Usage’view and using the ’Format’ Tab and inserting the Earned Value Fields, BCWS ACWS and BCWP via the ’Detali Styles.

    Also it can be seen it is calculating the fields correctly by going to the ’Report’Tab, Select ’Reports’ Select ’Cost Reports’ Select ’EV’ reports.

    I have a teleconference with Microsoft next Monday so hopefully we will see a resoultion on this very frustrating problem.

    I will keep the forum informed.

    Regards,

    Trevor.