Import P3 Basline/ Target in MSP2003
In the Open Standard
Damien GalllagherMember for 19 years 6 months
- Created
- 2
- 2
0
Dear Planners,
I have been asked to convert my programme from P3 to MSP2003. This was not a problem for the project schedule, but I am unable to bring my baseline with me.
Is there away I can use my P3 Baseline on my MSP2003 project? To my knowledge MSP2003 creates the baseline from the data within the project, and does not use an external file as the baseline.
Any help appreciated!
I have been asked to convert my programme from P3 to MSP2003. This was not a problem for the project schedule, but I am unable to bring my baseline with me.
Is there away I can use my P3 Baseline on my MSP2003 project? To my knowledge MSP2003 creates the baseline from the data within the project, and does not use an external file as the baseline.
Any help appreciated!
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?