Import baseline from one file to another
In the Open Standard
Evgeny Z.Member for 18 years 9 months
- Created
- 6
- 5
0
Dear all,
I have the following dilemma:
I have several versions of the same project schedule in different files (schedule_v1.mpp, schedule_v2.mpp, schedule_v3.mpp). . One of the old ones I now want to use as a baseline in my current one. Unfortunately I did not baselined it back then. In my current schedule some of the tasks changed date, duration, some new were added and some were deleted.
Is there any way I can save a baseline on the old file and copy it across to the new one?
I have the following dilemma:
I have several versions of the same project schedule in different files (schedule_v1.mpp, schedule_v2.mpp, schedule_v3.mpp). . One of the old ones I now want to use as a baseline in my current one. Unfortunately I did not baselined it back then. In my current schedule some of the tasks changed date, duration, some new were added and some were deleted.
Is there any way I can save a baseline on the old file and copy it across to the new one?
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?