data-date line colour

Jon WardMember for 18 years 4 months
Created
2
15
0
,, also,, how do you display the data-date line as a different colour? eg, bright red in the Gant chart??

2 replies

Oldest first
  1. 0
    Dave Turnbull ·
    Right click on the Gantt Chart, click Gridlines and then current date. Change colour as you want.

    Is this what you were after?
  2. 0
    Jon Ward ·
    your the man,, thanks Dave