Total Slack

Stuart AtkinsonMember for 22 years 9 months
Created
2
5
0
Gents,

Why am I getting Total Slack values of 49.56, why are they not whole numbers. I am sure it will be calendar or workday related. Can someone please explain the fix. P.S.Using MSP 2007.

Thanks,

Stuart

2 replies

Oldest first
  1. 0
    Darren Kosa ·
    Hi Stuart,

    I don’t use 2k7, but I’ve experienced similar problems in 2k3.

    Most of them have been down to work / units driving the durations or split tasks affecting the start times of successors.

    Try changing the date format to include hh/mm and then looking at the Start / Finish dates to see if anything stands out.

    My default Start / Finish times are 08:00 and 17:00 so if I now see a Start or Finish that doesn’t fit in with that (excluding half days), then I’m pretty sure something is amiss.

    Regards,

    Darren
  2. 0
    Stuart Atkinson ·
    Thanks Darren,

    I will investigate