How to track a bunch of unrelated activities?
In the Open Standard
Evgeny Z.Member for 18 years 9 months
- Created
- 5
- 3
0
Hi everyone,
I need your advice on how to track the following activities.
There is a task for engineer to update / create a bunch of documents. There is no specific sequence in which they have to be done, also engineer may switch between documents.
But I have the following requirements:
• I need to be able to estimate the total amount of work (duration) needed for the whole activity.
• I need to be able to track completing of individual documents.
One thing I could have done is to put a schedule, where all documents need to be done one after another, but I do not want to force a specific sequence on engineer, it needs to be flexible. So, if would start working from the last document, I would have to change the schedule to update it.
Any ideas how it can be done?
I need your advice on how to track the following activities.
There is a task for engineer to update / create a bunch of documents. There is no specific sequence in which they have to be done, also engineer may switch between documents.
But I have the following requirements:
• I need to be able to estimate the total amount of work (duration) needed for the whole activity.
• I need to be able to track completing of individual documents.
One thing I could have done is to put a schedule, where all documents need to be done one after another, but I do not want to force a specific sequence on engineer, it needs to be flexible. So, if would start working from the last document, I would have to change the schedule to update it.
Any ideas how it can be done?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?