Critical task
In the Open Standard
Christopher PaulrajMember for 17 years 8 months
- Created
- 1
- 3
0
Hi
The free slack for a particular task is 0 days, but still in my programme it doesn’t appear like a critical task, when I go to view-more views- detail Gantt.
Can someone let me know what the reason behind this is? Even I checked in tools menu – options – calculation – tasks are critical if slack is equal or less than 0……..
The free slack for a particular task is 0 days, but still in my programme it doesn’t appear like a critical task, when I go to view-more views- detail Gantt.
Can someone let me know what the reason behind this is? Even I checked in tools menu – options – calculation – tasks are critical if slack is equal or less than 0……..
1 reply
Oldest firstLog in or join to reply