Critical task

Christopher PaulrajMember for 17 years 8 months
Created
1
3
0
Hi

The free slack for a particular task is 0 days, but still in my programme it doesn’t appear like a critical task, when I go to view-more views- detail Gantt.

Can someone let me know what the reason behind this is? Even I checked in tools menu – options – calculation – tasks are critical if slack is equal or less than 0……..

1 reply

Oldest first
  1. 0
    Darren Kosa ·
    Hi Chris,

    I think you might be confusing Free Slack with Total Slack.

    Free Slack (or Free Float) is the time available in a project network before a preceding task(s) delays the start date of succeeding task(s).

    Total Slack (or Total Float) is the time available in a project network before a task delays the project end date.

    Free Float can be 0days and not on be the critical path, whereas tasks with 0days Total Float will be.

    Regards,

    Darren

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?