Decimals In Finish Variance

Vijayasarthty SMember for 20 years 3 months
Created
2
2
0
Dear All,

I am currently working with MSP 2007 and i find that after updating my schedule, the finish variance is getting displayed in decimals. Is there any way of rectifying it, my client is insisting in a finish variance without decimals and the gant chart together.
Kindly reply it this is possible to be done in MSP.

Regards,

Vijay

2 replies

Oldest first
  1. 0
    Darren Kosa ·
    Hi Vijay,

    I use a pretty simple formula to round up Work, so I’ve adapted it to do the same with Finish Variance for you.

    Tools > Customize > Fields

    Select a spare Text Field to customise and copy and paste this formula.

    ROUND([Finish Variance]/480) & " days"

    Hopefully this is what you’re after.

    Regards,

    Darren
  2. 0
    Vijayasarthty S ·
    Thanks for your response, i will try the same and check how my client responds to it, i will post the result on the fopum too.

    Regards,

    Vijay