How to make A Base line in MSP ?

A.Jaffer SadiqMember for 18 years
Created
3
2
0
hi

How to make A Base line in MSP ?
can u giv some idea
ok.

Thx. & Reg.
jaffer

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Jaffer,
    in MSP baseline is stored in the same project file; click Tools, Tracking, Save baseline (Define baseline in MSP2K), then select "Initial Plan" (or Initial Baseline?)
    Alexandre
  2. 0
    Joseph Erwin Cargason, C.E.,PSP ·

    Good evening I am trying the

    Good evening I am trying the above option but in MS2k7 the option are only

     

    "Tools - Tracking - Set baseline " there is no save baseline option,

     

    please advised if there is missing on my installed MSP.

     

     

    Hoping for your kind reply.

     

    joseph

  3. 0
    Evgeny Z. ·

    Jaffer,to set baseline is

    Jaffer,

    to set baseline is actually to save baseline

    You can save 11 baselines in Microsoft Project (Baseline (0), Baseline 1 – Baseline 10).

    The good practice is that you save baselines to Baseline 1 – Baseline 10 and keep Baseline (0) as a placeholder for comparison.

    In another words, if you want to compare your current plan with one of the baselines you have saved, you copy the Baseline X you want to compare your project with to a Baseline (0) (Tools=>Tracking =>Set Baseline => Set interim plan => Copy Baseline X into Baseline).

    This is because by default MS Project offers filelds, which compare current project only with Baseline (0), e.g. start variance, duration variance etc. To compare your current project with Baseline1-Baseline10 you need to define user fields, so it is easire just to copy it to Baseline (0)

    Regards.

    Evgeny

Log in or join to reply