Week Numbers in Bar Styles required

Philip KearneyMember for 24 years 7 months
Created
11
5
0
Hi,

Having searched thru the records/archives for a similar thread, couldn’t find the answer I’m looking for!
So what I am looking for is probably complicated!...
Here goes for nothing...

On my gantt chart I want week numbers on the left side of the bars. I have my timeline on top showing the week numbers but having a bit of data on my programme, I would like to show the week number that each activity is at for quick reference for the client. I know how to show dates etc but not good enough...The client is interested in seeing his project activities referred by week numbers.
I have thought about lookaheads & mini schedules but bollocks to that as it’s un-neccessary work.
I have checked through the functions/options etc. but to no avail.
Someone out there knows that this can be done.
So thanks in advance!

11 replies

Oldest first
  1. 0
    Trevor Rabey ·
    This sounds like something that is completely unnecessary but was just whimsically dreamed up by your client without any regard for whether it is useful or even possible. But, ultimately, anything is possible if someone is paying for it.

    Do you mean the week number since the project start date or the week number of the year?

    See Format, Layout for the format of the dates that appear on the bars. There are week number formats at the bottom of the list, but they are the week numer of the year. If it’s in the drop-down list you can have it and if not then you can’t.
    Except that if you use a spare Start field and a spare text field you can do the necessary calculation with the available fields and functions, and format it any way you like, and use that field as the left hand bar text in the Bar Styles definition.
    Having said how I would go about it, I haven’t actually done it, but leave it to you or someone who has the spare time to have go. Hope this helps.
  2. 0
    Philip Kearney ·
    Trevor,
    Thanks for taking the time to explain it twice! LOL!
    Yeah, its the weeks of the year I want to put in.
    Had a hunch that this was something to calculate but don’t have the inclination to go about it as quite busy at work these days!
    I will give your idea a go later so thanks again!
  3. 0
    Philip Kearney ·
    Trevor,

    Had a look at that, I’m not sure about that format as I don’t understand where first digit is coming from? For example it shows 1/Wk45...? What is with the 1/????
    Any ideas?
  4. 0
    Darren Kosa ·
    Hi Phillip,

    Are the Week numbers your client wants displayed the MS Project fiscal year (starts in Jan ends Dec) or from contract award/project start?

    For the fiscal year you could customise a spare text field and use this formula

    "W" & Format(DateAdd("d",7-Weekday([Finish]),[Finish]),"ww")

    Regards,

    Darren
  5. 0
    Philip Kearney ·
    Darren,

    If I could, I would drag you to the pub to buy you a few beers for that!
    Many thanks for that as it worked!
  6. 0
    Darren Kosa ·
    Phillip,

    If I could claim it as my own I would, but the person you’ll have to buy the beer for is a guy called Jack Dahlgren. He posted it somewhere a few years ago, I can’t remember where, but any formulae I see that may be of use at a later date I tend to squirrel away until it’s needed.

    I’ll keep any plaudits for passing it on though ;o)

    Regards,

    Darren
  7. 0
    Hemanth Kumar ·
    Hi Darren
    thanks for sharing the formula
    but when i insert there is 1 week difference
    week 50 is showing as 51
    when i put a -1 in the formula everything works fine
    except week 52 , which becomes CW-0 ??
    why ?
    any tweaks ?

    regards
    hemant
  8. 0
    Hemanth Kumar ·

    Here is the sample file

    http://rapidshare.com/files/244313154/Calendar_Weeks.mpp
  9. 0
    Lalit Sis ·
    Philip,

    There can be another simple formula:-

    "Wk " & Int(ProjDateDiff([Project Start],[Start],"Standard")/60/8/5)

    HTH
  10. 0
    Philip Kearney ·
    Lalit,

    thanks for that, I have validated it & it works fine so will be keeping it handy for future reference.

    Keep up the fine work, everybody!
  11. 0
    L.E.N. Lewis ·
    Using a hardcoded constant such as "60*8*5" is not a good idea. The number of hours in a day or the number of hours in a week is controlled by Tools > Options > Calendar tab.

    You should replace the hardcoded constants with either of [Minutes Per Week] or [Minutes Per Day] depending on your circumstances.