Week numbers

Richard EmmsMember for 13 years 4 months
Created
1
3
0

Dear Forum

I wonder if someone can help me.  I like the week numbers to count down during the preconstruction period then count back up during the construction phase.  I like the week numbers to be shown as -3,-2,-1,1,2,3,4,5,6,etc.  However, when I adjust the project start date to the first date of the construction phase the pre-cosntruction phase 'takes ownership' of the intended start date and 'thinks' the pre-construction commences at that time.  With Asta you can set zero date and I was wonderin if there such a function with Microsoft Project.

 

Any help will be welcome.

1 reply

Oldest first
  1. 0
    Richard Emms ·

    Thank you for your reply.

    Thank you for your reply. I have tried that option and it's close of what I like MS to do. What I like is for MS project to count down the pre-construction phase e.g week -3, week -2, week -1 during the pre construction phase. Then count up week 1, week 2, week 3 etc as normal from the start of the actual construction work. Thank you

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?