Indent/Outdent of activities in MS Project

Raul SantosMember for 16 years 11 months
Created
1
3
0
I am trying to indent/outdent some activities in an existing schedule but I am receiving the following message from the software:

”The outline change would create a circular relationship.
Indenting these tasks would create an illegal relationship with other tasks.
Check the task dependencies for the tasks from which you are indenting, and then try again.”

Can anyone help me to solve this issue?

1 reply

Oldest first
  1. 0
    Trevor Rabey ·
    It looks self explanatory, doesn’t it?
    Look at the task that you are about to make into a heading by indenting the other tasks under it.
    It will have predecessors and/or successors.
    Remove them.
    Now indent the other tasks and it will be ok.
    You cannot have a task whose predecessor or successor is its own heading. It would be like linking a task to itself.