add fileds to a PWA view

Assaf FMember for 18 years 9 months
Created
2
3
0
Hi,
I would like to add the predecessors & successors fileds to a project view in the PWA.
It seems that these fileds are not in the list.
Is there a way to display them?

Thanks,
Assaf.

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Assaf,
    if a field you want to add to a PWA view is not available in the field list, you have to know how to use Microsoft development tools to develop new PWA views
    Alexandre
  2. 0
    Assaf F ·
    I tried to create a new view (using manage views)but the fields are just not there.