Dynamic Task Buffer and ALAP tasks
In the Open Standard
Eric ReddingMember for 16 years 8 months
- Created
- 3
- 4
0
Hello all,
I want to dynamically link an ALAP task to a buffer (an internal buffer, not a project buffer). When I do so and recalculate, the ALAP task drifts to the end of the project.
How can I dynamically link and keep the ALAP task that is a predec. of the buffer in its proper timed place?
Be well and thanks,
Eric
I want to dynamically link an ALAP task to a buffer (an internal buffer, not a project buffer). When I do so and recalculate, the ALAP task drifts to the end of the project.
How can I dynamically link and keep the ALAP task that is a predec. of the buffer in its proper timed place?
Be well and thanks,
Eric
3 replies
Oldest firstLog in or join to reply