Roll Up Resource Names

Neil GartlandMember for 16 years 7 months
Created
4
3
0
Is it possible within the Resource Names column, to roll up resource names to summary tasks so that if three resources had been used on different tasks in a group, these three names would be displayed on the summary line in the resouce names column.

I know it is possible to access this information through other views but want to know if it is possible to customise this view?

Any assistance appreciated

Thanks

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Neil,
    this indeed a FAQ! it is only possible to roll up resource names by writing a macro
    however, I would not roll up my resource names in the Resource Name column, as it would duplicate the resource workload at work package (summary task) level; if necessary, use a custom text field instead
    Alexandre
  2. 0
    Neil Gartland ·
    Thanks Alexandre, good point about rolling up to the Resource Names column, do you know where I might find an example of a macro that would do this please?

    Thanks
  3. 0
    Alexandre Faulx-Briole ·
    Neil,
    I remember having seen such a macro a few years ago, but I do not know were; that’s too bad!
    Have a look at the MSP newsgroups
    Alexandre
  4. 0
    Rafael Davila ·
    MAYBE THIS IS WHAT YOU ARE LOOKING FOR.

    Format the bar chart portion of a Gantt view:

    http://office.microsoft.com/en-us/project/HA012253681033.aspx

    Go to Display task names for individual .......

    Have some issues with overlapping tasks, unless can be fully resolved I would avoid using this at all.

    Roll up resources

    Hope this helps.

    R. Davila