Attaching comments to tasks

Craig AdamsMember for 20 years
Created
2
3
0
Hello,

I am trying to attach a text comment to a baseline task, anyone have any ideas?

Have been able to make the comment easy enough but not to get it to hang on to the baseline bar.

Appreciate your assistance.

Regards,

Craig

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Craig,
    MSP (any version up to 2010) lets you attach an object (text box or graphical object) either to a task or a date; by "task", it means the schedule bar, not he baseline
    It is not possible to attach any object to a baseline bar; since the baseline bar is not supposed to move, I would attach my text box to a specific date, say the baseline start
    Alexandre
  2. 0
    Craig Adams ·
    Thanks, thought about it on way home and realized attaching dialog box to a task that has slipped (by way of jistorical record and visual reminder (until the slipped task is finished) was the way to go.

    Cheers.