Critical milestone

Dan MårtenssonMember for 16 years 8 months
Created
3
2
0
Hello,

Can anyone tell me how to make a critical milestone red in MSP?

Thanks

Dan

3 replies

Oldest first
  1. 0
    Gary Whitehead ·
    1) Right click on the bar chart, go to "Bar Styles"
    2) Insert a new row BELOW the existing milestone row
    3) select appearance, including colour
    4) In ’Show for’ Column, enter "Milestone,Critical"
    5) Enter either Start or Finish in BOTH ’From’ and ’To’ fields


    Cheers,

    G