A quick question re updating baseline
In the Open Standard
Stephen DevauxMember for 21 years 6 months
- Created
- 1
- 2
0
I have a client who is looking at software tools. I am NOT by any means a software expert, so please be gentle. http://www.planningplanet.com/images/icon_frown.gif
I’m curious as to how easy the following is to do in MS Project:
(a) I have a baseline plan of 5 five-day activities as follows:
A5 -> B5 -> C5 -> D5 -> E5
(b) I then create for my team a working plan with 5 four-day activities plus a schedule reserve of 5 days, as follows:
A4 -> B4 -> C4 -> D4 -> E4 -> SR5
My question: as I work to (b) and report progress against it, how easy is it to simultaneously update my baseline plan? Do I have to do double-entry and re-type the updates, or is there some way to pass on the updates automatically?
Fraternally in project management,
Steve the Bajan
I’m curious as to how easy the following is to do in MS Project:
(a) I have a baseline plan of 5 five-day activities as follows:
A5 -> B5 -> C5 -> D5 -> E5
(b) I then create for my team a working plan with 5 four-day activities plus a schedule reserve of 5 days, as follows:
A4 -> B4 -> C4 -> D4 -> E4 -> SR5
My question: as I work to (b) and report progress against it, how easy is it to simultaneously update my baseline plan? Do I have to do double-entry and re-type the updates, or is there some way to pass on the updates automatically?
Fraternally in project management,
Steve the Bajan
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?