MSP 2010

Susiri LeelaratnaMember for 21 years 8 months
Created
8
2
0
When I print out MSP2010 file of 2.7 MB, the file size increases to 99 MB during transmission to the printer (The output at the printer indicates the file size).
It takes about 15 minutes to print.

What is the reason for this?

Can anyone help?

8 replies

Oldest first
  1. 0
    Andrew Dick ·
    Susiri,
    This problem may come about by having information below your project.
    In the activities view go to the bottom line. From there highlight everything below it to the bottom row, then clear or delete these lines to remove any data that may be in there.

    This should hopefully fix the issue.

    Andy
  2. 0
    Susiri Leelaratna ·

    Thanks Andrew. We have found

    Thanks Andrew.

    We have found the problem. It was in the printer software.

    Regards

  3. 0
    Susiri Leelaratna ·

    When I use "Group by summary"

    When I use "Group by summary" in MSP 2010, the summary task in the DURATION FIELD does not calculate as previously did in MSP2007:

    Duration in Summary Task (MSP 2010) = Duration of the sub task with MAXIMUM Duration

    Duration in Summary Task (MSP 2007) = Latest date of any sub task - Earliest date of any sub task

    How do I overcome this problem in MSP 2010?

  4. 0
    Niek Zonneveld ·

    Susiri,This is clearly an

    Susiri,

    This is clearly an error. I've tried to produce similar results with formula's (ProjDateDiff, between earliest start and latest finish date in the summary) but that doesn't work (like it should) either.

    If you (temporarily) remove your baseline, you can use Duration Variance instead but that's obviously not the way to go in the long run.

    H.T.H.

  5. 0
    Raja Ghosal ·

    Hi, After updating the

    Hi,

     

    After updating the project progress I want to see expected finish date on a current data date.Can anyone help me in MSP 2010.???????????

  6. 0
    Evgeny Z. ·

    RE<< When I use "Group by

    RE

    << 

    When I use "Group by summary" in MSP 2010, the summary task in the DURATION FIELD does not calculate as previously did in MSP2007:

    Duration in Summary Task (MSP 2010) = Duration of the sub task with MAXIMUM Duration

    Duration in Summary Task (MSP 2007) = Latest date of any sub task - Earliest date of any sub task

    How do I overcome this problem in MSP 2010?

    >> 

    I think you need to use scheduled duration field.

    I think this has been discussed here:

    http://www.planningplanet.com/forums/microsoft-project/534833/group-duration-summary

  7. 0
    K L Kameswari Akondi ·

    Susiri, first convert the

    Susiri,

    first convert the file into pdf and then give a print

  8. 0
    Leonard Esber ·

    Hi all, just want to ask how

    Hi all, just want to ask how many columns available in MS Project 2010?