BCWP is lower than expected.......my SPI is below 1
In the Open Standard
Sam TanMember for 15 years 10 months
- Created
- 0
- 3
0
Hello,
i'm trying to do EVM for a project for the month of November. i filled in the actual hours for all my tasks for the month.....(for all the people), and put zero actuals when that task was not worked on but was scheduled to be worked on.
now, when i'm looking at my "Task sheet", i see the following. (i'm concerned about the second major tasks in bold). I know we're not behind schedule but how can i increase my BCWP to artificially increase my SPI?
| BCWS | BCWP | ACWP | SV | CV |
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| $60,841.86 | $60,670.96 | $48,947.07 | ($170.89) | $11,723.89 |
| $45,791.52 | $38,638.56 | $28,839.89 | ($7,152.96) | $9,798.67 |
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?