Printing errors

Federico EscaloraMember for 17 years 10 months
Created
5
5
0

hello to everyone,

I need some help, this is the situation,why when I do printing for Microsoft program its apper ( THERES IS NOT ENOUGH MEMORY TO COMPLETE THE OPERATION ) even when I restart to my PC then reprint again nothing change i? Can you please  help me ,What I will do to printing such as having a problem, anyway  my activity is 1,700 plus activity. Please kindly email  to fescalora@yahoo.com.   Thanks  in advance .

 

Thanks and Regards,

fescalora

5 replies

Oldest first
  1. 0
    Ahmad Husni Saleh Karimi ·

    I do have the same

    I do have the same problem,

    any friend can help us.

  2. 0
    Federico Escalora ·

    Try to convert it to MS 2003,

    Try to convert it to MS 2003, same problem also with me, my program is MS 2007, but when I convert it to 2003 it works, just try.

  3. 0
    Ahmad Husni Saleh Karimi ·

    TQ i will try

    TQ i will try

  4. 0
    Matthew Lin ·

    Fescalora, - go to "project",

    Fescalora,

    - go to "project", make sure project start date consistent with real start date; guess that current date there is much earlier than the actual one

    - go to "file" then "print", make sure timescale is "all"

    - pls double check your page setup via print preview

    After that, print should be ok.

    If it still doesn't work, pls create a new project then copy & paste the entire project, do the set-up again;

    pls be aware of activities with constraints...

     

    Good Luck,

  5. 0
    Alexandre Faulx-Briole ·

    Federico,looks like a bug in

    Federico,

    looks like a bug in your project file; it appears some time when the mpp file is spoiled

    do you have the same error with all your files?

    if yes, you should reinstall the software from scratch; if no, carefully copy the project data in a new blank file, and cross fingers

    Hope it will work and help

    Alexandre