Dear all,

 

How can I introduce actual % complete to MS Project to get Duration delay?

 

Regards

4 replies

Oldest first
  1. 0
    Darren Kosa ·

    Hi Ahmed, This is probably a

    Hi Ahmed,

    This is probably a very simplistic solution, but have you tried experimenting with 'Types' and using fixing work / effort driven when updating actuals?

    Regards,

    Darren

  2. 0
    Trevor Rabey ·

    I know what % Complete is. It

    I know what % Complete is. It is just the actual duration divided by the total duration. So if you have a 10 day task and 6 days of actual duration and 4 days of remaining duration, then % Complete = 60%. But I don't know what you mean by "duration delay". What is it?

  3. 0
    Kumar Baiju ·

    Hi Alll       I am new for

    Hi Alll

          I am new for this forum and i ahve no idea how can add any question to this. I have one question about the actual duratin in MS project-2003. i am using 24 hous calander. whan i updated my actual duration Eg 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. i cannot understand why in summary it comes only nearly one fourth duration

    4.83 Hrs 2.41 Hrs
    20 Hrs 10 Hrs
       
  4. 0
    Kumar Baiju ·

    Hi Alll       I am new for

    Hi Alll

          I am new for this forum and i ahve no idea how can add any question to this. I have one question about the actual duratin in MS project-2003. i am using 24 hous calander. whan i updated my actual duration Eg 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. i cannot understand why in summary it comes only nearly one fourth duration

    4.83 Hrs 2.41 Hrs
    20 Hrs 10 Hrs
       