Summary Tasks Resource Calendars & Tools/Options/Calendar HELP

Eric ReddingMember for 16 years 8 months
Created
3
6
0

Hello all,

I want the summary tasks to reflect the amount of time it will take to perform the work under them.  If I have a couple of 24 hr tasks (determined by the task calendar) and some "standard" tasks under the same summary task, I cannot obtain a summary task duration that makes sense.

If I change the calendar in Tools/Options to 24 hours it affects the entire schedule.  Not what I want.

If I apply resources to tasks that are 24 hour resources or standard calendar resources or 10 hour resources, the "calculation" of the summary task duration doesn't make sense.

In setting up a project with many task calendars and unique resource calendars, what will the summary task's duration reflect?  I thought it would describe the amount of time it will take to perform all of the tasks.  But if I look at the start and finish dates and compare those to the summary task's duration it doesn't add up.

Your help is appreciated.

Eric

3 replies

Oldest first
  1. 0
    Kumar Baiju ·

    Hello Eric    I have also

    Hello Eric

       I have also same problem, you can also see the post in this forum " activity shows only one fourth duration" , you also find the solution.

     

    Regards\\

  2. 0
    Eric Redding ·

    thank you for your response.

    thank you for your response.  The video did not answer my question of having several calendars applied to tasks beneath a summary task and having the summary task correctly display the duration and time interval of the child tasks.

  3. 0
    Eric Redding ·

    Hello, What I have learned in

    Hello,

    What I have learned in the past hour.  If I have a group of tasks that have different task calendars applied to them, I have to enter the task durations appropriately.  See the first group of tasks below.  This string of tasks should take 7 days.  The next group of tasks has 1 change.  I changed the 24h/day task from 72 hours to 3 days.  MS Project is "thinking" that due to Tools/Options/Calendar that a day equals 8 hours then if the 3 day task is 3x8 and the task calendar says "let's work this task 24 hours straight" then it will take only 1 day to complete.  Left at 72 hours it took, correctly, 3 calendar days. (keep in mind if you are performing 'what-if' challenges to the schedule.  you might want to see the effect of a previously worked 3 day task is you were to apply resources to it working 24 hrs/day remembering that a "day" is defined in Tools/Options/Calendar)

    Other groups of tasks below also had one duration change with similar effect.