As an occassional user of Microsoft i have a query

 

Is there any way of setting up week numbers ie period numbering options from a specific date ie project start date

 

Any help is appreciated

 

Thanks

 

Regards

 

[Topic moved to MSP forum by Gary W]

3 replies

Oldest first
  1. 0
    Matthew Lin ·

    Alan, In timescale option

    Alan,

    In timescale option (right click timescale in bar area), choose bottom tier format as " W1, W2 ...", whether from start or finish.

    In middle tier, choose week/month to indicate date period.

    You can even have 3 tiers by show three tier in the timescale option

    Rgds,
    Matthew

  2. 0
    Alan Robson ·

    Matthew Thanks for your

    Matthew

    Thanks for your help

    Regards

    Alan

     

     

  3. 0
    Maarten van Wyk ·

    Hi guys,   I'm

    Hi guys,

     

    I'm currently working with a quite big project plan in MS Project 2007. I want to move over to MS Project 2010 and had it installed, but it does not want to open my MS Project 2007 plan. It just starts up and then close immediately. Any ideas of what it could be and how to fix it?

     

    Any suggestions would be appreciated.

     

    Kind Regards,

    Maarten